The implementation concerned the construction of main switchboards for the project of reconstruction of laboratory rooms in the buildings of the water treatment station in the heat and power plant.

Project Implementation – Water Treatment Station

The implementation concerned the construction of main switchboards for the project of reconstruction of laboratory rooms in the buildings of the water treatment station in the heat and power plant. We delivered 3 main switchboards to the facility along with equipment, cabling and other aesthetic elements that are visible in the photos. Additionally, the order included the delivery of 7 facility switchboards and active participation in FAT acceptance.

Supply voltage: 230/400V AC
Control voltage: 24V AC/DC
Rated current: 630A
Tightness class: IP55
Corrosion protection: C2
Operating temperature range: -20°C to 40°C
Completion date: January 2021

Switchboard:

Dimensions: 1360 x 1920 x 400mm
Color: RAL7035
Manufacturer: Radiolex
810-067 – TwinLine-W – Free-standing cabinet, insulation class I

ABB equipment used:
  • 1SCA151068R1001 – OXB630E3X4QT – Automatic transfer switch 630A
  • 1SEP101890R0002 – XLP 00-6BC 160A – 3P fuse switch 160A
  • 1SEP620010R3020 – ZLBM00-3P-V – 3P 160A fuse strip switch
  • 1SEP620011R3020 – ZLBM1-3P-V – 3P 250A fuse strip switch
  • 2CSG113220R4001 – VLM-1-500/96 – 500V panel voltmeter
  • 2CSG299883R4052 – M2M – Power quality analyzer
  • 2CTB815101R0700 – OVR T1 3N 25-255 TS – Surge arrester class B type 1 3P+N